Ten men build a wall in 30 days. How long willit take 6 (six) men to buitd the same wall.
Solución de inteligencia artificial de Upstudy
Responder
Solución
Respondido por UpStudy AI y revisado por un tutor profesional


Beyond the Answer
If ten men can build a wall in 30 days, they can finish it by completing 1/30 of the wall each day. Therefore, the total work needed (measured in man-days) is 10 men x 30 days = 300 man-days. If 6 men are working on the same wall, the number of days they would take can be calculated as follows: 300 man-days ÷ 6 men = 50 days. So, it will take 6 men 50 days to build the same wall. Remember, the efficiency of your workforce matters! If working with teams, always ensure everyone is motivated – a happy worker builds faster! Also, double-check your calculations, as it’s easy to misplace a digit or skip a step.