Pregunta
upstudy study bank question image url

If 30 men can complete a work in 40 days then in how many days 15 men will comple charge that porter charges to carry a bag of 50 kg of rice to a distance of 4 km is Rs 200 What is the charge to carry the bag of 30 kg of rice to a distance of 10 km ? 200 labourers need 50 days to construct a road of 4 km long. How many labourers are needed construct the 8 km long road in 80 days? If 30 men can do a piece of work in 11 days working 9 hours a day. For how many hours a de 55 men have to work in order to finish the work in 18 days?

Ask by Medina Bright. in Nepal
Dec 03,2024

Solución de inteligencia artificial de Upstudy

Respuesta verificada por el tutor

Responder

1. 15 men will take 80 days to complete the work. 2. The charge to carry the 30 kg bag of rice for 10 km is Rs 300. 3. 250 labourers are needed to construct the 8 km long road in 80 days. 4. 55 men have to work 3 hours a day to finish the work in 18 days.

Solución

Let's solve each of the problems step by step. ### Problem 1: Work Completion by Men If 30 men can complete a work in 40 days, we can find out how many days 15 men will take to complete the same work. 1. **Total Work**: \[ \text{Total Work} = \text{Number of Men} \times \text{Number of Days} = 30 \text{ men} \times 40 \text{ days} = 1200 \text{ man-days} \] 2. **Days for 15 Men**: \[ \text{Days} = \frac{\text{Total Work}}{\text{Number of Men}} = \frac{1200 \text{ man-days}}{15 \text{ men}} = 80 \text{ days} \] So, **15 men will take 80 days** to complete the work. ### Problem 2: Charge for Carrying Rice The porter charges Rs 200 to carry a 50 kg bag of rice for 4 km. We need to find the charge for a 30 kg bag for 10 km. 1. **Charge per kg per km**: \[ \text{Charge per kg for 4 km} = \frac{200 \text{ Rs}}{50 \text{ kg}} = 4 \text{ Rs/kg} \] \[ \text{Charge per kg per km} = \frac{4 \text{ Rs}}{4 \text{ km}} = 1 \text{ Rs/kg/km} \] 2. **Charge for 30 kg for 10 km**: \[ \text{Charge} = 30 \text{ kg} \times 10 \text{ km} \times 1 \text{ Rs/kg/km} = 300 \text{ Rs} \] So, the charge to carry the 30 kg bag of rice for 10 km is **Rs 300**. ### Problem 3: Labourers Needed for Road Construction 200 labourers can construct a 4 km long road in 50 days. We need to find out how many labourers are needed to construct an 8 km long road in 80 days. 1. **Total Work in Labour-days**: \[ \text{Total Work} = \text{Number of Labourers} \times \text{Number of Days} = 200 \text{ labourers} \times 50 \text{ days} = 10000 \text{ labour-days} \] 2. **Work Rate**: \[ \text{Work Rate} = \frac{10000 \text{ labour-days}}{4 \text{ km}} = 2500 \text{ labour-days/km} \] 3. **Total Work for 8 km**: \[ \text{Total Work for 8 km} = 2500 \text{ labour-days/km} \times 8 \text{ km} = 20000 \text{ labour-days} \] 4. **Labourers Needed for 80 Days**: \[ \text{Labourers} = \frac{\text{Total Work}}{\text{Number of Days}} = \frac{20000 \text{ labour-days}}{80 \text{ days}} = 250 \text{ labourers} \] So, **250 labourers are needed** to construct the 8 km long road in 80 days. ### Problem 4: Hours of Work for 55 Men If 30 men can do a piece of work in 11 days working 9 hours a day, we need to find out how many hours a day 55 men have to work to finish the work in 18 days. 1. **Total Work in Man-Hours**: \[ \text{Total Work} = \text{Number of Men} \times \text{Number of Days} \times \text{Hours per Day} = 30 \text{ men} \times 11 \text{ days} \times 9 \text{ hours/day} = 2970 \text{ man-hours} \] 2. **Hours per Day for 55 Men in 18 Days**: \[ \text{Hours per Day} = \frac{\text{Total Work}}{\text{Number of Men} \times \text{Number of Days}} = \frac{2970 \text{ man-hours}}{55 \text{ men} \times 18 \text{ days}} = \frac{2970}{990} = 3 \text{ hours/day} \] So, **55 men have to work 3 hours a day** to finish the work in 18 days.

Respondido por UpStudy AI y revisado por un tutor profesional

error msg
Explicar
Simplifique esta solución

Beyond the Answer

To tackle the first question, we know that work done is directly proportional to the number of men and the number of days they work. If 30 men finish the work in 40 days, then 15 men will take double the time, which means 80 days. Isn’t it fascinating how manpower and time play such an essential role in project management? Now, regarding the porter charge, if carrying a 50 kg bag costs Rs 200 for 4 km, we can easily calculate that the cost per kg per km is Rs 10. For a 30 kg bag over 10 km, the charge would be Rs 300 (30 kg x 10 km x Rs 1), showcasing how simple calculations can allow us to budget for resources efficiently. When it comes to labor, if 200 laborers can finish 4 km in 50 days, to find out how many are needed for 8 km in 80 days, you can use the formula: (Workers x Days) / Distance = Constant. As a fun fact, doubling both distance and time results in needing the same number of workers - so, 200 laborers are still needed, just longer to build that longer road! Lastly, for 55 men to finish the job in 18 days, you would first calculate the total work done by 30 men in the original scenario and then divide it by the number of men (55) to see how many hours they need to work each day to complete it in the desired timeframe. It boils down to working through the numbers systematically, which can be quite rewarding!

¡Prueba Premium ahora!
¡Prueba Premium y hazle a Thoth AI preguntas de matemáticas ilimitadas ahora!
Quizas mas tarde Hazte Premium
Estudiar puede ser una verdadera lucha
¿Por qué no estudiarlo en UpStudy?
Seleccione su plan a continuación
Prima

Puedes disfrutar

Empieza ahora
  • Explicaciones paso a paso
  • Tutores expertos en vivo 24/7
  • Número ilimitado de preguntas
  • Sin interrupciones
  • Acceso completo a Respuesta y Solución
  • Acceso completo al chat de PDF, al chat de UpStudy y al chat de navegación
Básico

Totalmente gratis pero limitado

  • Solución limitada
Bienvenido a ¡Estudia ahora!
Inicie sesión para continuar con el recorrido de Thoth AI Chat
Continuar con correo electrónico
O continuar con
Al hacer clic en "Iniciar sesión", acepta nuestros términos y condiciones. Términos de Uso & Política de privacidad