Megan wants to have an extension built on her house. She is told it will take 8 builders 28 days to build the extension. How many builders would Megan need to hire if she wanted her extension built in 16 days?

Ask by Vargas Bond. in the United Kingdom
Nov 06,2024

Solución de inteligencia artificial de Upstudy

Respuesta verificada por el tutor

Responder

Megan would need to hire 14 builders to complete the extension in 16 days.

Solución

To determine how many builders Megan would need to hire to complete the extension in 16 days, we can use the concept of work done, which is based on the number of builders and the time taken. First, we calculate the total amount of work required to build the extension in terms of builder-days. Given: - 8 builders take 28 days to complete the work. Total work in builder-days = Number of builders × Number of days \[ \text{Total work} = 8 \text{ builders} \times 28 \text{ days} = 224 \text{ builder-days} \] Now, if Megan wants to complete the work in 16 days, we can find out how many builders she would need by dividing the total work by the number of days she wants to complete it in. Let \( x \) be the number of builders needed: \[ x \text{ builders} \times 16 \text{ days} = 224 \text{ builder-days} \] Now, solve for \( x \): \[ x = \frac{224 \text{ builder-days}}{16 \text{ days}} = 14 \text{ builders} \] Therefore, Megan would need to hire **14 builders** to complete the extension in 16 days.

Respondido por UpStudy AI y revisado por un tutor profesional

error msg
Explicar
Simplifique esta solución

The Deep Dive

To solve this problem, we can start by figuring out the total builder-days needed to complete the project. Since 8 builders can finish the extension in 28 days, the total builder-days required is: \[ 8 \text{ builders} \times 28 \text{ days} = 224 \text{ builder-days} \] Now, if Megan wants the extension built in 16 days, we can determine how many builders she needs by dividing the total builder-days by the new time frame: \[ \frac{224 \text{ builder-days}}{16 \text{ days}} = 14 \text{ builders} \] So, Megan would need to hire 14 builders to complete the extension in 16 days.

preguntas relacionadas

Latest Arithmetic Questions

¡Prueba Premium ahora!
¡Prueba Premium y hazle a Thoth AI preguntas de matemáticas ilimitadas ahora!
Quizas mas tarde Hazte Premium
Estudiar puede ser una verdadera lucha
¿Por qué no estudiarlo en UpStudy?
Seleccione su plan a continuación
Prima

Puedes disfrutar

Empieza ahora
  • Explicaciones paso a paso
  • Tutores expertos en vivo 24/7
  • Número ilimitado de preguntas
  • Sin interrupciones
  • Acceso completo a Respuesta y Solución
  • Acceso completo al chat de PDF, al chat de UpStudy y al chat de navegación
Básico

Totalmente gratis pero limitado

  • Solución limitada
Bienvenido a ¡Estudia ahora!
Inicie sesión para continuar con el recorrido de Thoth AI Chat
Continuar con correo electrónico
O continuar con
Al hacer clic en "Iniciar sesión", acepta nuestros términos y condiciones. Términos de Uso & Política de privacidad