Megan wants to have an extension built on her house. She is told it will take 8 builders 28 days to build the extension. How many builders would Megan need to hire if she wanted her extension built in 16 days?
Solución de inteligencia artificial de Upstudy
Responder
Solución
Respondido por UpStudy AI y revisado por un tutor profesional


The Deep Dive
To solve this problem, we can start by figuring out the total builder-days needed to complete the project. Since 8 builders can finish the extension in 28 days, the total builder-days required is: \[ 8 \text{ builders} \times 28 \text{ days} = 224 \text{ builder-days} \] Now, if Megan wants the extension built in 16 days, we can determine how many builders she needs by dividing the total builder-days by the new time frame: \[ \frac{224 \text{ builder-days}}{16 \text{ days}} = 14 \text{ builders} \] So, Megan would need to hire 14 builders to complete the extension in 16 days.